The Seven Phase
Restoration Program for the
Adelaida School
Phase 1: Provide on-site electric, phone and water services.
COMPLETED
Phase 2: New foundation under schoolhouse
Estimated Cost: $140,000
Phase 3: Septic system including leach lines and temporary bathroom
hookups
Partially Completed
Phase 4: Site work, grading and base parking area, concrete walks,
BBQ area
Estimated Cost: $30,000
Phase 5: Rebuild exterior walls, exterior siding as necessary to
prepare for new roof construction, new wiring in these walls
Estimated Cost: $125,000
Phase 6: Rebuild roof framing, overhead electrical wiring, ceiling
and new roof
Estimated Cost: $50,000
Phase 7: Finishing phase: rebuild kitchen and bathrooms, renovate
blackboards, rebuild foyer, repair or replace windows and doors,
paint, and landscaping.
Estimated Cost: $40,000 to $75,000
TOTAL EST. COST OF RESTORATION:
$425,000 to $460,000
|